Our Services

External Inspection
External inspection are required every two (2) years from date of commissioning.
SCOPE OF WORK:
-
Clean Vessel.
-
Record all data information.
-
Check all welds & fittings for leaks.
-
Check operation of SRV and Pressure Gauge.
-
Check drain.
-
Check if Vessel is bolted down.
-
Record NDT measurements.
-
Issue Compliance Certificate.

Internal Inspection
Internal Inspections are required every four (4) years from date of commissioning.
SCOPE OF WORK:
Includes External Inspection with addition of the following:
-
Isolate and drain the unit.
-
Remove and replace Safety Relief Valve.
-
Access the Vessel internally and view the internal condition and welds.
-
Clean the Vessel internally.
-
Replace all gaskets/fittings used to access the Vessel.
-
Start compressor and record operating pressures.
-
Record NDT measurements.
-
Issue Compliance Certificate.

Safety Relief Valve Testing And Certification
Conformance to Australian Standard AS1271-2003 and the provisions of the ASME Boiler & Pressure Vessel Code Section VIII Division 1.
Scope of work:
We understand the importance of having plant that is utilised in a variety of ways operate as it should in the workplace - which is why we offer our safety relief valve testing and certification both onsite and offsite.
We minimise downtime and increase confidence by testing and certifying a range of safety relief valves on site, which are then issued with a certificate of conformance.

.
.